Amur Gas Processing Plant
The investor and customer of the Amur GPP construction project is Gazprom Pererabotka Blagoveshchensk LLC (part of the Gazprom Group).
Construction work on the Amur GPP began in October 2015.
The plant was launched on June 9, 2021.
Full capacity is scheduled to be reached by January 1, 2025.
The plant specializes in extracting methane-related gases from natural gas: ethane, propane, butane and other heavier hydrocarbon fractions, as well as helium, which is supplied to the helium hub in Vladivostok. It is expected that after reaching full capacity, the Amur GPP will become the second largest in terms of natural gas processing volume (42 billion m³ per year) and the largest in the world in terms of helium production (up to 60 million m³ per year).
In the immediate vicinity of the GPP, in August 2020, SIBUR began construction of the Amur GCC.
Key project participants:
Construction management is carried out by the general contractor, NIPIGAZ, part of the SIBUR Group.
The company's scope of work includes design, preparation of working documentation, supply of equipment and materials, execution of construction and installation works, and transfer of the plant to Gazprom Pererabotka Blagoveshchensk LLC in a state of mechanical readiness.
Linde AG was the supplier of the main process equipment for the Amur GPP for cryogenic gas separation to produce helium and valuable components for petrochemistry until 2022.
Also, in 2016-2017, Chinese companies China Petroleum Engineering & Construction Corporation, Sinopec, Gezhouba Group and others were involved in the project.
China Petroleum Engineering & Construction Corporation will design, manufacture, supply equipment and build booster compressor shops, gas drying and purification units, and gas fractionation units at the Amur GPP.
The Tecnimont and Sinopec consortium was selected as the EPC contractor following an open competitive procedure for the design, procurement and construction of off-site facilities.
The bulk of the subcontracted construction and installation work will be performed by Renaissance Heavy Industries LLC.
Maire Tecnimont Group is an international EPC contractor specializing in the construction of gas processing and petrochemical facilities. The company operates in 30 countries, including Russia.
Sinopec Engineering Group is one of the leading engineering companies in China. It is part of the Chinese petrochemical group Sinopec Corp.
Renaissance Heavy Industries is part of Rönesans Holding, which operates in Turkey, the CIS, Europe, the Middle East and North Africa and is one of the largest general contractors for construction in Russia.
The Amur GPP is an important link in the technological chain of natural gas supplies to China via the "eastern" route under the largest contract in history. The plant will receive multi-component gas from the Yakutsk and Irkutsk gas production centers, which Gazprom is creating as part of the Eastern Gas Program, via the Power of Siberia gas pipeline.
Contact us to find out about current job openings on the project!
Projects
-
Solar Energy Projects
MPH Vostok cooperates with several companies in the field of solar generation, one of...
-
Sakhalin-2
Sakhalin-2 is a project to develop the Piltun-Astokhskoye oil and Lunskoye gas condensate...
-
Gold Mining Industry
Projects in the gold mining industry are implemented by our Client - the largest investor...
-
ZapSibNeftekhim
ZapSibNeftekhim is a Tobolsk enterprise of SIBUR, the largest petrochemical complex...
-
Olefin Complex EP-600 Project & Styrene Chain Project (NKNKh)
Nizhnekamskneftekhim PJSC is one of SIBUR's largest production sites for synthetic rubbers...
-
Subsea Technologies and Repair - Center of Excellence
Effective integrity management of offshore gas transportation infrastructure is essential...
-
YAMAL LNG
YAMAL LNG is an integrated project for the production, liquefaction and supply of natural...
-
Taishet Anode Factory
Taishet Anode Factory (TAF) is one of RUSAL's two largest investment projects in the...
-
Salym Oil Fields Development Project
The Salym project is a complex of works on additional exploration and development of...
-
Ferzikovo Project
Ferzikovo cement plant in Kaluga region was launched in 2014. The unique Borshchevskoye...
-
VOLGA Project
The Volsky Plant (1897) is not only one of the largest plants in the Russian cement...
-
KOS – Kazanorgsintez
Kazanorgsintez PJSC is one of the leading enterprises of the chemical industry of...
-
RusVinyl
RusVinyl LLC is a polyvinyl chloride (PVC) manufacturing company in the Kstovsky District...
-
NPP Rooppur
The first NPP in Bangladesh, Rooppur, with two VVER-1200 reactors with a total capacity...
-
El Dabaa NPP
El Dabaa NPP is the first nuclear power plant in Egypt, which will be built in the...
-
Paks-2 NPP Construction Project
The Paks-2 NPP construction project is being implemented on the basis of the Russian-Hungarian...
-
Arctic LNG 2
Arctic LNG 2 is a project of Novatek for the extraction of natural gas and the production...
-
Baltic Project
The Baltic Project is a project for a large complex for processing ethane-containing...
-
Amur Gas Chemical Complex
The Amur Gas Chemical Complex (GCC) is one of SIBUR's priority projects. It is a joint...
-
Amur Gas Processing Plant
The investor and customer of the Amur GPP construction project is Gazprom Pererabotka...
-
Baimskaya Copper Project
The Baimskaya copper-porphyry area is located in the Bilibinsky district of the Chukotka...
-
Turkish Stream
Turkstream is a main export gas pipeline from Russia to Turkey across the Black Sea....
-
KHARYAGA
Type of Project: Oil Onshore Project The Kharyaga oilfield lies 60 kilometres...